Solution Question 3

Excavators

 

 

Assume bucket capacity = 3m3

 

From graph the bulked output of a wheeled loading shovel= 235 m3/ hr

 

In place output = bulked output/swell factor = 235/1.25 = 188 m3I hr Production losses = 10%

therefore actual output = 0.9 x 188 = 169.2 m3/ hr

 

Total time required to remove earth = 180,000/169.2 = 1064 hours

 

Contract time= 8 weeks x 5 days x 10 hours I day= 400 hours

 

Number of loading shovels= 1064/400 = 2.66 (Use 3 wheeled loading shovels)

 

Trucks

 

 

Truck capacity =  5 x bucket size= 15m'

Loading time = truck volume I bulked production rate = 15/ 235 hours = 3.8 min. Travel time to tip and back = 1.5 miles x 2115 hours  = 12 min.

Number of trucks required = 1 +(travel time+ dumping time)

loading time

 

 

= 1 +(12+4)=   4.25

                                        4

 

 

use 5 trucks per loading shovel

 

 

 

 